Families, Children & Learning – Capital Budget Summary

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 5

Month 5

Month 5

Month 5

£'000

Service

£'000

£'000

£’000

£'000

£'000

£'000

£'000

%

0

Health, SEN & Disability Services

43

0

0

0

43

43

0

0%

0

Education & Skills

37,374

0

0

0

37,374

37,374

0

0%

0

Children’s Safeguarding & Care

35

0

0

0

35

35

0

0%

0

Schools

122

0

0

0

122

122

0

0%

0

Total Families, Children & Learning

37,574

0

0

0

37,574

37,574

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

Health, SEN & Disability Services

 

 

 

None Reported

 

 

 

Education and Skills

 

 

 

None Reported

 

 

 

Children’s Safeguarding & Care

 

 

 

None Reported

 

 

 

Schools

 

 

 

None Reported

 

 

 

 


Health & Adult Social Care – Capital Budget Summary

 

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 5

Month 5

Month 5

Month 5

£'000

Service

£'000

£'000

£’000

£'000

£'000

£'000

£'000

%

0

Adult Social Care

338

0

0

267

605

605

0

0%

0

Total Health & Adult Social Care

0

0

0

267

605

605

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

Adult Social Care

 

 

 

 

 

 

 

Variation

267

Ireland Lodge Building Works

Modernisation funding to support the delivery of the modernisation of the Learning Disabilities team at Ireland Lodge.

 


Economy, Environment & Culture (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 5

Month 5

Month 5

Month 5

£'000

Service

£'000

38£'000

£’000

£'000

£'000

£'000

£'000

%

0

Transport

34,296

0

380

0

34,676

34,676

0

0%

0

City Environmental Management

3,931

2,600

120

(30)

6,621

6,621

0

0%

0

City Development & Regen

9.035

0

0

(1,530)

7,505

7,505

0

0%

0

Culture, Tourism & Sport

10,770

0

0

0

10,770

10,770

0

0%

0

Property

6,282

0

0

(265)

6,017

6,017

0

0%

0

Total Economy, Environment & Culture

64,314

2,600

500

(1,825)

65,589

65,589

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

 

 

 

 

City Environmental Management

 

 

 

Reported at Other Committees

2,600

Stanmer Park Restoration Project

Reported in January 2018 with update on 25 June 2019 for contract award. Project commenced in summer 2019.

Variation

(30)

Investment in City Parks

Variation of budget less than £0.100m.

City Development & Regeneration

 

 

 

Reprofile

(1,530)

Housing Joint Venture

Due to delays in obtaining planning permission for the first two sites under consideration by the Homes for the City of Brighton & Hove LLP (Joint Venture), the programme of delivery has had to be moved back by two months. Works are not expected to commence until later in the year, therefore the contribution required in 2019/20 is lower than previously estimated.

 

Property

 

 

 

Reprofile

(265)

Bartholomew House Cladding and Windows Replacement

Delays in finding a suitable procurement route for the project will mean that the project is now expected to span two financial years.

 


Neighbourhood, Communities & Housing (excluding Housing Revenue Account) – Capital Budget Summary

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 5

Month 5

Month 5

Month 5

£'000

Service

£'000

£'000

£’000

£'000

£'000

£'000

£'000

%

0

Housing – General Fund

4,485

0

0

0

4,485

4,485

0

0%

0

Libraries

310

0

0

(9)

301

301

0

0%

0

Total Neighbourhood, Communities & Housing

4,795

0

0

(9)

4,786

4,786

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

Libraries

 

 

 

Variation

(9)

Hove Library Redevelopment

Variation of budget less than £0.100m.

 


Housing Revenue Account (HRA) – Capital Budget Summary

 

Forecast Variance Month 2

Unit

Reported Budget Month 2

Reported at Other Committees

New Schemes

Variations, Slippages & Reprofiles

Reported Budget Month 5

Forecast Outturn Month 5

Forecast Variance Month 5

Forecast Variance Month 5

£'000

£'000

£'000

£'000

£'000

£'000

£'000

£'000

%

186

City Development & Regeneration

8,210

0

0

(1,515)

6,695

6,800

105

1.6%

(353)

Housing Revenue Account

41,233

0

0

(879)

40,354

39,720

(634)

-1.6%

(167)

Total Housing Revenue Account

49,443

0

0

(2,394)

47,049

46,520

(529)

-1.1%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

Amount
£'000

Project

Description

City Development & Regeneration

Reprofile

(549)

Selsfield Drive

The due diligence process undertaken to agree the Agreed Maximum Price resulted in a delay to the start of the main construction works. Construction works are expected to begin in July and are due for completion in autumn 2020.

Reprofile

(224)

Buckley Close

Completion of the project is due in the summer of 2020. The reprofile reflects the updated project delivery timeline, which had been delayed due to the discovery of asbestos and unforeseen structural works to the main retaining wall.

Reprofile

(742)

Victoria Road

The project team are currently reviewing costs and delivery with an anticipated start date in January 2020. Completion of the sports pavilion is expected in July 2020.

Variance

105

Various Schemes

Variances of under £0.100m across the following schemes:
£0.072m Redevelopment of HRA Vacant Garage Sites
£0.002m Brookmead Site Development
£0.023m Wellsbourne Development
£0.008m Lynchet Close

Housing Revenue Account

Variation

(265)

Roofing

Savings delivered against the Major Projects budget, mainly as a result of the final cost of works being less than estimated.

Variation

(250)

Doors

Further to an update to Housing & New Homes Committee in September 2018 the manufacture of fire doors has been restricted. A British Standard testing method for fire doors has now been agreed however there is currently a lack of manufacturers that have compliant products. The council is managing the replacement doors in line with fire risk assessments and developing a replacement programme which is expected to commence in 2020.

Variation

(200)

Environmental Improvements

The Environmental Improvements Budget of £0.400m is currently included within the capital programme.  However, the types of works being carried out are largely of a revenue nature and the funding is being adjusted to reflect this and added to the £0.100m in the revenue budget.

Variation

(314)

Fire Safety

Consultation with residents has led to changes to the specification for spinkler installations in two blocks in the city. As a result the project is now in line to commence in quarter four and forecasts have been adjusted to reflect this. There is sufficient budget already profiled to 2020/21 to fund the remaining project costs.

Variation

315

Communal Boilers

Transfer of budget to allow for replacement of Heat Interface Units at Nettleton & Dudeney in this financial year (previously planned for 2020/21) to be aligned with a plant room upgrade which is currently being carried out. Undertaking this at the same time will reduce inconvenience for residents.

Variation

(100)

Structural Repairs

Savings delivered against the Major Projects budget, mainly as a result of the final cost of works being less than estimated.

Variation

(240)

Home Energy Efficiency & Renewables

Solarise projects are being delivered across several financial years meaning some spend will occur in the 2020/21 financial year. In addition, due to delays in a European Regional Development Fund funding bid with the University of Brighton, including capital match funding, means spend will occur in the next financial year.

Variation

250

Kitchens

There has been an increase in the number of referrals for replacement kitchens and bathrooms through the repairs service which are delivered alongside the planned programme for maintaining council housing stock to the Decent Homes Standard. In addition, a higher than forecast number of customers are choosing to have a kitchen which results in a higher spend.

Reprofile

(75)

Home Energy Efficiency & Renewables

Reprofile of under £0.100m.

Variance

(275)

Other Mechanical & Electrical

The procurement of a new fire alarms contract has resulted in a delay to the proposed capital works programme for this year. Changes to the sprinkler installation programme following consultation with residents has impacted on expenditure for cold water mains; a programme for the removal of water tanks is continuing over the second half of the year.

Variance

(226)

Structural Repairs

Savings delivered against the Major Projects budget, mainly as a result of the final cost of works being less than estimated.

Variance

(133)

Various Schemes

Variances of under £0.100m across the following schemes:
£(0.005m) Roofing
£(0.097m) Windows
£0.005m Doors
£0.074m Feasibility and Design - P&I
£(0.044m) Fire Safety
£(0.052m) Insulation
£0.050m External Decorations & Repairs
£(0.076m) Tilbury Place
£0.012m Bathrooms

 


Finance & Resources - Capital Budget Summary

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 5

Month 5

Month 5

Month 5

£'000

Service

£'000

£'000

£’000

£'000

£'000

£'000

£'000

%

0

IT & D

1,972

0

0

(9)

1,963

1,963

0

0%

 

 

 

 

 

 

 

 

 

 

0

Total Finance & Resources

1,972

0

0

(9)

1,963

1,963

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

Finance & Resources

 

 

 

Variation

(9)

IT Programme Costs

 

Variation of budget less than £0.100m

 


Strategy Governance & Law - Capital Budget Summary

 

Forecast

 

2019/20

Reported

New

Variation,

2019/20

Forecast

Forecast

Forecast

Variance

 

Budget

At Other

Schemes

Slippage/

Budget

Outturn

Variance

Variance

Month 2

 

Month 2

Committees

(App. 6)

Reprofile

Month 2

Month 2

Month 2

Month 12

£'000

Service

£'000

£'000

£’000

£'000

£'000

£'000

£'000

%

0

Life Events

6

0

0

0

6

6

0

0%

0

Perf Improvement & Programmes

1,807

0

0

0

1,807

1,807

0

0%

0

Total Strategy Governance & Law

1,813

0

0

0

1,813

1,813

0

0%

 

Details of Variation requests and explanations of significant Forecast Variances, Slippage or Reprofiles are given below:

 

Detail Type

£'000

Project

Description

Strategy, Governance & Law

 

 

 

No budget changes to report

for Month 2

 

 

 

 

Note: There are currently no capital budgets to report on for Corporate Budgets.